Reconstruction of Street Water Pipes

The site includes reconstruction and rehabilitation of street water pipes with destruction and restoration of the asphalt pavement. Reconstruction and rehabilitation of the water pipe with pipes with diameters Ф90, Ф110 and Ф140, with a total length of 8,572 m, was carried out.

The necessary building water supply diversions were built:
132 pcs. above-ground fire hydrants, 290 pcs. shut-off valves, fittings and connections to existing branches and sections. The total excavation of the construction is 9,900 m³. The asphalt pavement with the laying of 5,800 m² of solid asphalt concrete has been restored.